Daily report checklist for hotel projects

Hotel projects, new or renovation, are tracked room by room and often run while guests are in the building. The daily report should record progress by room and floor, protection of guest areas and the FF&E deliveries that drive turnover.

What makes these jobs different

  • Room by room tracking with repetitive scopes
  • Renovations often occur on occupied properties
  • Brand standards and Property Improvement Plan (PIP) items on renovations
  • FF&E deliveries and installation drive room turnover
  • Noise and work hours limited around guests

Who reads this report

ReaderWhat they look for
Owner or asset managerrooms turned over and cost exposure
Hotel general managerfloors out of service and guest impact
Brand representativePIP items and brand standards
FF&E purchasing agentdeliveries, damage and shortages

The checklist

Progress

  • Rooms and floors completed by trade
  • Rooms turned over to the owner

Occupied property

  • Floors out of service
  • Guest area protection and signage
  • Noise work and timing

People

  • Manpower and hours by sub

FF&E and deliveries

  • FF&E delivered, damaged or missing
  • Storage and staging

Owner and brand

  • Brand or owner walk findings
  • PIP items completed

Records

  • Photos by room
  • Delays from FF&E or room release

Requirements vary by contract, owner and jurisdiction. Use this as a starting checklist.

Risks to document every day

  • Late FF&E
  • Rooms not released on schedule by hotel operations
  • Brand changes
  • Damage in finished rooms

Or text it in

Floor 6 rooms 601-618. Paint done 601-610, carpet started 601-604. 15 on site: 6 paint, 4 flooring, 5 FF&E. 3 headboards damaged on delivery, pics. Floor 7 released by hotel ops tomorrow.

Superintendents and foremen text their day and Cascade Technology turns it into the daily report. Subcontractor access is free.

Frequently asked questions

How should a hotel renovation daily report track work?

By room and floor for each trade, with rooms turned over noted daily. Add floors out of service and guest area protection when the hotel is operating.

Why record FF&E deliveries on the daily report?

FF&E often decides when a room can be turned over. Logging what arrived, what was damaged and what is missing keeps turnover dates realistic.

Request Access

CHECKLIST / HOTEL

See how your team reports by text.

Free onboarding and integration, a one-month pilot and no contract lock-in. Tell us about your jobsites.

EARLY ACCESS FOR PUGET SOUND GCS · SET UP IN DAYS · YOUR DATA STAYS YOURS

Daily report checklist for hotel projects

Project
Date and completed by

Progress

  • Rooms and floors completed by trade
  • Rooms turned over to the owner

Occupied property

  • Floors out of service
  • Guest area protection and signage
  • Noise work and timing

People

  • Manpower and hours by sub

FF&E and deliveries

  • FF&E delivered, damaged or missing
  • Storage and staging

Owner and brand

  • Brand or owner walk findings
  • PIP items completed

Records

  • Photos by room
  • Delays from FF&E or room release